Current Status
On The Hard
The yacht club is allowing Hydrotherapy to stay on the hard while the renovation backlog is worked down.
Current Status
The yacht club is allowing Hydrotherapy to stay on the hard while the renovation backlog is worked down.
Current Work
The main refit work list now starts with the on-the-hard jobs: deck work, deck painting, bottom work, rudder fit-up, and mounting the motor before slip day.
Next Milestone
The next real milestone is moving Hydrotherapy into the slip around July 17, 2026 if the on-the-hard work is ready.
Target First Sail
The target first sail is August 1, 2026 after the in-slip electrical, systems, rigging, and dockside checks are finished.
Current Timeline
The main work list now starts with the jobs that need dry access while Hydrotherapy stays on the hard.
Once Hydrotherapy is in the slip, the focus shifts to the jobs that must still be finished before first sail.
Splash and first sail are now two separate milestones, with a dockside commissioning stretch between them.
The nice-to-have interior cosmetic and comfort work no longer needs to block the first sail target.
What Could Move The Date
Working Schedule
Now Through Late June
Work through the deck structure, cockpit areas, bottom-side access, valves, and other jobs that need the boat dry and open.
Late June Through Mid-July
Finish the paint-heavy work, fit or replace the rudder, mount the motor, and close the final dry-side launch prep before the move.
Around Jul 17
Hydrotherapy moves into the slip around July 17 only if the on-the-hard work and launch checks are closed cleanly.
Jul 18 Through Jul 31
Use the slip time for electrical proving, fuel and valve checks, rigging and safety setup, and the dockside systems review before sail.
Target Date
First sail stays separate from splash day. August 1 is the target only if the in-slip systems and safety work are signed off.
After First Sail
Interior cosmetic work, locker clean-up, comfort upgrades, and the less time-critical extras can move to the post-sail phase.
Current Project Status
Hydrotherapy is staying on the hard while the deck, paint, bottom, rudder, and motor jobs that need dry access are worked down first.
Once the hard-stand jobs are closed, the slip phase becomes the place for electrical, rigging, fuel, and dockside checks before first sail.
July 17 is the working slip target, and August 1 is the target first sail. The gallery below still reflects the current Hydro photo archive while that sequence gets worked down.
Featured Gallery