Phase Codes
OH / IS / AF
Each job is grouped by when it should happen: on the hard, in the slip, or after the first sail.
Phase Codes
Each job is grouped by when it should happen: on the hard, in the slip, or after the first sail.
OH
Jobs to finish while Hydrotherapy is still dry, including deck, bottom, rudder, valve, and motor work.
IS
Dockside work after launch, focused on systems, rigging, safety, and checks needed before first sail.
AF
Cosmetic, comfort, and lower-priority follow-up jobs that can wait until after the boat has sailed.
OH On The Hard
Moisture-map the deck, open the problem zones, and repair the wet coring and related structural sections that still control the hard-phase schedule.
Repair the mast-step area and inspect the compression-post-related structure while the deck is already open and accessible.
Repair the sliding companionway hatch core and stiffeners, then close the hatch hardware, latch, and hinge issues while the joinery and deck edges are accessible.
Work through the wet cockpit lids and related lids first so those areas are structurally ready before paint and before the move to the slip.
Seal the deck penetrations properly, install the backing plates, and rebed the stanchion bases and critical deck hardware before the finished surfaces are closed up.
Replace or refit the lifelines and any wrong or loose deck hardware as part of the hard-phase structural and deck-safety closeout.
Remove the failed recoats, fair the repaired surfaces, then complete primer, topcoat, nonskid, and cure time before launch prep begins.
Use the hard for the bottom, keel, and hull-adjacent work, including the keel-bolt torque review and any dry-side findings that should be settled before slip day.
This now sits in the OH phase. Replace the gate valves with the proper setup and use the dry access to inspect the hoses, backing areas, and connections before launch.
Finish the rudder replacement or rebuild, fit the tiller, and confirm sweep, clearance, and alignment before Hydrotherapy moves to the slip.
Mount the motor, secure the fuel tank and related launch-side fuel details, and make sure the engine side of the project is ready for the slip phase.
Replace the cracked escape hatch glazing, secure the loose deckhead light, close hatch hardware snags, and settle the remaining dry-side issues before the move.
Service the winches and review the remaining deck-gear items so normal use does not begin with obvious maintenance still outstanding.
IS In The Slip Before First Sail
Use the first slip days to confirm that the hull, valves, bilges, and basic dockside conditions are stable before the rest of the commissioning work begins.
Finish the battery, wiring, panel, breaker, switch, and shore-power cleanup, then prove the circuits at the dock before Hydrotherapy goes sailing.
Use the slip time for bilge proving, manual pump hose confirmation, lights, VHF, and the rest of the dockside systems checks that still sit between launch and sail.
Finish the back stay setup, confirm the steering under load, and review the lifelines and related deck-safety gear before the first sail window.
Mount the extinguishers, settle the life-ring compliance issue, add smoke and CO protection, and make sure the visible safety items are actually ready before Hydrotherapy sails.
Use the slip phase to confirm the motor installation, fuel behavior, and dockside controls so the first sail does not start with unresolved engine-side questions.
Use a final dockside review to clear the remaining snags and keep August 1 tied to actual readiness instead of just the calendar.
AF After First Sail
Use this phase for the cabin-side tidy-up work, locker paint, wire labeling clean-up, and the cosmetic details that matter but do not need to block first sail.
Cushion refreshes, cockpit comfort upgrades, and other living-space improvements can sit here unless they become part of a safety issue later.
Extras like AIS, NMEA 2000, battery monitoring, USB charging, fans, and solar can all stay outside the core pre-sail path and be scheduled later.
Name graphics, striping, and the final presentation details can follow first sail once the boat is already back in normal use.
Ground tackle upgrades, optional winch changes, running-rigging extras, and other value-add items belong here unless you later decide they should move forward.
Use the first sail and the first few outings to decide what actually deserves another project phase instead of guessing too early from the hard or the slip.