Target Slip Date
April 25
The working target for getting Hydrotherapy back into the slip on April 25, 2026. This is not a first-use date.
Target Slip Date
The working target for getting Hydrotherapy back into the slip on April 25, 2026. This is not a first-use date.
Current Work
Deck repair prep is active now, along with the must-do launch items: rudder replacement, bottom sanding and anti-fouling paint, and a keel bolt torque check.
Next Milestone
Hydrotherapy needs to be back in the slip first. The actual fiberglass repairs begin after that.
Sale Target
August 1, 2026 is the working sail target. July 17 stays a stretch case only if the post-slip work goes exceptionally cleanly.
Current Timeline
The structural repair area is still being opened, mapped, and cleaned so the real fiberglass work can happen after Hydrotherapy is back in the slip.
These jobs still have to be done before Hydrotherapy goes back in the water.
The actual fiberglass repairs now start only after the boat is back in the slip.
April 25 is the in-slip milestone. August 1 is the working sail target if the post-slip work stays controlled.
What Could Move The Date
Updated April-to-August Gantt chart. It now shows what must be finished before April 25, what starts after Hydrotherapy is back in the slip, and how that flows into the August 1 sail plan.
Working Schedule
This schedule is now being tracked as one active path: finish the pre-slip prep, put Hydrotherapy back in the slip on April 25, then move into the fiberglass repairs and follow-up work that support an August 1 sail plan.
The active plan is to finish only the prep work and launch-critical items before April 25, get Hydrotherapy back in the slip, and then start the actual fiberglass repairs afterward. August 1 is the working sail target if the post-slip repair path stays controlled.
Now
Remove rotten core, clean back to sound structure, confirm repair boundaries, and stage the repair plan. No actual fiberglass repair goes in before the boat is back in the slip.
Early To Mid April
Install and fit the new rudder that was picked up yesterday, then confirm the steering setup is ready for launch.
Mid April
Sand the bottom, apply anti-fouling paint, and check torque on the keel bolts before launch week closes in.
Apr 25
The project target is to have the boat put back in the slip on April 25. That is a placement date, not a sail date, and not a promise that the boat is ready for normal use that day.
Late April Through June
Once the boat is back in the slip, do the actual fiberglass structural work, allow cure time, and move through fairing and sealing as needed.
July
Wrap the punch-list items, clean up presentation details, and work toward an August 1 sail-ready handoff.
Current Project Status
These updates are meant to help someone new understand the build quickly: what work is active now, what stage comes next, and what changes actually affect the April 25 slip target and the August 1 sail plan.
The opened sections are still being cleaned up and mapped so the later glass work can be done after launch. At the same time, the pre-slip list now includes installing the new rudder, bottom sanding and anti-fouling paint, and checking keel bolt torque.
April 25 is the handoff from launch prep into dockside repair work. Once the boat is back in the slip, the fiberglass rebuild, cure time, and finish work can move forward.
One date tracks when the boat is back in the water. The other tracks when the repair, cleanup, and presentation work might support a sail. The gallery below now reflects only the Hydro photos you want kept on the site.
Featured Gallery
These images now come directly from the curated Hydro archive folders you kept. Click any image to enlarge it or open the full archive.